Here’s why this latest move from West Bengal is a sentiment negative for BHEL


Shares of Bharat Heavy Electricals Ltd. (BHEL) were trading more than 2% lower on Monday, November 23, after the West Bengal Electricity Regulatory Commission (WBERC) approved a proposal to remove the mandatory domestic sourcing requirement for boilers, turbines and generators (BTG) for a new coal-based power project in the state.

The regulator has allowed the project’s developer to procure the main plant equipment from overseas suppliers for the proposed third 1×800 MW coal-fired power plant in West Bengal. The decision follows a petition filed by the state’s distribution utility.

The regulator cited limited participation in the tender, with only three bidders submitting bids. It also said that prospective bidders had raised concerns over the ability of domestic manufacturers to meet delivery timelines because of their existing order books.

Another factor considered was the 60-month execution timeline for the project. India’s model bidding guidelines mandate domestic sourcing of BTG equipment only when power supply is scheduled to commence within three years.

However, the permission comes with certain conditions. Imported equipment must comply with the Ministry of Power’s order dated July 2, 2020, Indian boiler regulations and Central Electricity Authority (CEA) standards.

The project developer will also have to bear the customs duty and foreign exchange risks associated with importing the equipment. Domestic manufacturers remain eligible to supply the equipment, and the developer can still choose Indian suppliers.

The WBERC clarified that the relaxation applies only to this particular power project and should not be treated as a precedent for other tenders.